RESOLUTION #09-143

Approving Horsfield Construction Pay Request #3 Re: 2009 South Cedar Street Reconstruction Project, in the amount of $386,991.61

WHEREAS, Horsfield Construction contracted with the City to complete reconstruction of South Cedar Street, and

WHEREAS, The above-referenced project is proceeding, and Horsfield has submitted their third pay request, and

WHEREAS, The City Engineer has recommended that the Contractor be paid the third installment on their contract with the City in the amount $386,991.61, and

WHEREAS, It appears that the pay request is appropriate.

NOW, THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve Pay Request #3 Re: 2009 South Cedar Street Reconstruction project, payable to Horsfield Construction in the amount of $386,991.61.