City of Monticello, Iowa
RESOLUTION #2025-82
Approving Change Order #4 in the increased amount of $23,025.82 as submitted by Bill Bruce Builders related to the Monticello Wastewater Treatment Plant Improvements
WHEREAS, Bill Bruce Builders is contracted with the City to complete the Monticello Wastewater Treatment Plant Improvements, and
WHEREAS, Bill Bruce Builders has submitted Change Order #4 tied to:
- Extending the stub wall along the back of the biosolids equipment building to further protect the precast building, and
- Replacing unsuitable soils encountered during installation of water and sewer mains within the treatment plant site.
WHEREAS, The City Engineer has reviewed the proposed Change Order #4 in the increased amount of $23,025.82 and recommends that it be approved by the City Council.
NOW THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve modified Change Order #4 submitted by Bill Bruce Builders related to the Monticello Wastewater Treatment Plant Improvements in the increased amount of $23,025.82.
IN THE TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal for the City of Monticello, Iowa to be affixed. Done this 16th day of June, 2025.
Wayne Peach, Mayor
Attest:
Sally Hinrichsen, City Clerk/Treasurer