City of Monticello, Iowa
RESOLUTION #2025-69
Approving Change Order #3 in the increased amount of $210,104.27,
as submitted by Bill Bruce Builders related to the Monticello
Wastewater Treatment Plant Improvements
WHEREAS, Bill Bruce Builders is contracted with the City to complete the Monticello Wastewater Treatment Plant Improvements, and
WHEREAS, Bill Bruce Builders has submitted Change Order #3 tied to:
- Adding materials and labor for controls integration between equipment and control panels;
- Adding/revising GFCI outlets for the air compressors system and polymer feed skid as well as adjusting a breaker from 20 amps to 30 amps;
- Replacing the existing grit control panel, additional conduit and wiring for a solenoid valve and new hand-off switch for the grit classifier;
- Remove and replace the existing circuit breaker in the screen building;
- Relocated sludge VFD’s to screen building.
WHEREAS, The City Engineer has reviewed the proposed Change Order #3 in the increased amount of $210,104.27 and recommends that it be approved by the City Council.
NOW THEREFORE, BE IT RESOLVED that the City Council of Monticello, Iowa does hereby approve modified Change Order #3 submitted by Bill Bruce Builders related to the Monticello Wastewater Treatment Plant Improvements in the increased amount of $210,104.27.
IN THE TESTIMONY WHEREOF, I have hereunto subscribed my name and caused the Great Seal for the City of Monticello, Iowa to be affixed. Done this 19th day of May, 2025.
Wayne Peach, Mayor
Attest:
Sally Hinrichsen, City Clerk/Treasurer